Soil Remediation of Formerly Utilized Sites, Remedial Action Program (FURAP)

MAJOR PROJECT TASKS:    

  • Clean-up of former nuclear power laboratory
  • Excavate, backfill, and dispose of 60,000 tons of impacted soil within a 20 day window
  • Install 8,000 SF of sheeting for safe excavation
  • Provide dust control
  • Trucking and disposal of contaminated material
  • Decontaminate all vehicles and equipment on site
  • Implementation of a site specific HASP

MAJOR PROJECT CONTAMINANTS:

  • VOCs
  • Heavy Metals

SIGNIFICANT PROJECT OBSTACLES:

  • Project time constraints

Location: Windsor, CT
Owner: Confidential
Engineer: O'Brien & Gere Engineers
Project total: $1,350,000